Hello Experts,
Please let me share the ideas of how should we go about this process. We are using PP-PI process here.
We have two furnaces having identical in capacity and feeding of materials X1 & X2, the final finished product would be coming through both X1 and X2. But we don't know from which furnace the FG material is coming through, ultimately we have been using one product from X1 and X2. How do we configure this scenario please share any thoughts, would be highly appreciable.
Thanks,
Srini