ChaRM: Normal Change Production import issue with 4 tier landscape

$
0
0

Charm Chamipons.

 

I facing issue in ChaRM: Normal Change workflow where we have 4 tier landscape(Dev-QA-PREPRD-PRD)

I am able move till ZMMJ: Successfully Tested " after the TR are Released and imported QA and Pre-Production manually using taslkist for Regression Test and set with status Regression testing,once the Regression testing is done we go for Production Cab status for CAB approval.

 

Once CAB is approved(ServiceNow) status moves to Authorized for Production and set the project phase to Go-Live with that when i ci go to SCMA to import the TR is PRD i am getting sucesfully compelted but the TR is not imported and getting below message "

 

Downgrade check begins

Downgrade check passed

Downgrade check ends

Current phase of project: Go-Live

Action to be checked: Schedule Manager: Import into Production

Start Import (Project DN6_P00016)...

There are no transport requests available for import

 

But When i keep the status " Sucessfully Tested " in Change Document level and Project with GoLive status i am able to import the TR into PRD.

 

ZMMJ NC -CD user profile status

NC_Status profile.jpg

 

 

But the Funtionality working fine in the Urgent wokflow.

Please can you help me with solution???????????

 

Regards

John.

 

 